96th and Brentwood Traffic Signal
The City of La Vista has begun the process of designing, and ultimately installing, a traffic signal at the intersection of 96th Street and Brentwood Drive. 

Following is a tentative schedule as of October 25, 2017:
  • Begin bidding process: November 8, 2017
  • Bid opening: November 28, 2017
  • Award bid: December 5, 2017
  • Begin construction: March 2018
  • Complete Construction: May 2018

As always with any construction project, things can change that could affect this timeline and we will update this page accordingly. 

For more information on this project, contact the Public Works Department, 402-331-8927. 